Acceptance Sampling: Single Sampling Plans, OC Curves and Risks

The decision problem

A receiving department gets a lot of N items. Inspecting every item may be too costly, too slow, or impossible if testing destroys the item. Acceptance sampling inspects a random sample and makes a lot-level decision: accept or reject.


It is a decision rule about lots, not a tool for estimating or improving a process over time (that is the job of process control methods).

Single sampling plans

A plan is written (n, c):


  1. Draw a random sample of n items from the lot.
  2. Count the defectives, d.
  3. If d ≤ c, accept the lot. If d > c, reject it.


The acceptance number c is a count of defective items in the sample, not a percentage.

Probability of acceptance

If the lot's fraction defective is p and the lot is large relative to the sample, the number of defectives in the sample is approximately binomial, so


Pa(p) = Σk=0c C(n, k) pk(1 − p)n−k


  • When n is large and p small, the Poisson approximation with λ = np is convenient: Pa ≈ Σk=0c e−λλk/k!
  • When the sample is a large fraction of a small lot, the hypergeometric distribution is exact.


Worked example. Plan n = 30, c = 1, lot fraction defective 3%.


  • P(0) = 0.9730 = 0.4010
  • P(1) = 30 × 0.03 × 0.9729 = 0.3721
  • Pa = 0.4010 + 0.3721 = 0.773


The same plan accepts a 10%-defective lot with probability 0.184. A Poisson illustration: for n = 100, c = 3 and p = 0.02, λ = 2 and Pa ≈ e−2(1 + 2 + 2 + 1.333) = 0.857.

The operating characteristic curve

Plotting Pa against p gives the plan's OC curve. It starts at 1 when p = 0 and falls as quality worsens. Its shape shows how well the plan discriminates:


  • Increasing n with c fixed makes the curve fall faster (stricter). At p = 0.03, n = 60 with c = 1 accepts with probability 0.459, versus 0.773 for n = 30.
  • Increasing c with n fixed makes the plan more lenient: n = 60 with c = 2 gives 0.731 at p = 0.03.
  • Increasing both in proportion makes the curve steeper around its midpoint, which means better discrimination between good and bad lots, at a higher inspection cost.

Two quality levels and two risks

Term

Meaning

Associated risk

AQL (acceptable quality level)

A fraction defective the consumer regards as satisfactory as a process average

Producer's risk α = 1 − Pa(AQL)

LTPD (lot tolerance percent defective), also called RQL

A fraction defective the consumer wants to reject

Consumer's risk β = Pa(LTPD)


Plans are often designed so that α is about 0.05 and β about 0.10.

Rectifying inspection

When rejected lots are 100% inspected and every defective found is replaced with a good item, the plan changes the quality of what is shipped onward:


  • Average outgoing quality: AOQ ≈ Pa · p · (N − n)/N. Accepted lots keep their uninspected defectives; rejected lots leave with none; the sampled items are cleaned either way.
  • AOQL: the maximum of AOQ over all p, a worst-case long-run outgoing quality.
  • Average total inspection: ATI = n + (1 − Pa)(N − n).


AOQ is small for very good lots (few defectives) and for very bad lots (almost always rejected and screened), so it peaks at an intermediate quality.



A receiving inspector uses a single sampling plan with n = 50 and c = 2. A random sample of 50 items from a lot of 1,200 contains 3 defective items.

What does the plan direct the inspector to do?

Choose an answer

Create a free account to get started

Unlock full course notes by signing up

  • Video lessons taught by top educators
  • Practice questions with guided solutions
  • Written review notes for reference
  • Expert answers anytime from course tutors

A supplier and a customer agree on a sampling plan with an acceptable quality level (AQL) of 1.5% defective and a lot tolerance percent defective (LTPD) of 6% defective.

Which quantity is the producer's risk of this plan?

Choose an answer

Create a free account to get started

Unlock full course notes by signing up

  • Video lessons taught by top educators
  • Practice questions with guided solutions
  • Written review notes for reference
  • Expert answers anytime from course tutors

A single sampling plan uses n = 20 and c = 1. Lots are large, so the binomial model applies.

What is the probability of accepting a lot whose fraction defective is 8%?

Choose an answer

Create a free account to get started

Unlock full course notes by signing up

  • Video lessons taught by top educators
  • Practice questions with guided solutions
  • Written review notes for reference
  • Expert answers anytime from course tutors