Project Planning and Control: difficulty 3

Mark Yourself Question

  1. Grab a piece of paper and try this problem yourself.
  2. When you're done, check the "I have answered this question" box below.
  3. View the solution and report whether you got it right or wrong.

A deliverable planned for 12 May is 60% complete on that date; the owner estimates five more working days are needed, while the next dependent task was planned to start 13 May. Write a short control update that states the variance, one assumption, the forecasted consequence, and a next decision. Do not silently change the baseline.