Mark Yourself Question
For a proposed new feature discovered after planning: (a) name two pieces of information needed before estimating its impact; (b) state who should own the analysis versus who should authorize a baseline change; and (c) explain why “we can fit it in somehow” is not adequate control evidence.
Unlock full course notes by signing up
Project Planning and Control: difficulty 3
A deliverable planned for 12 May is 60% complete on that date; the owner estimates five more working days are needed, while the next dependent task was planned to start 13 May. Write a short control update that states the variance, one assumption, the forecasted consequence, and a next decision. Do not silently change the baseline.